RIB LAKE SCHOOL DISTRICT
EXECUTIVE SUMMARY
PROVIDED BY FINDORFF
1200 North Street, Rib Lake, WI 01.23.2026

A bird's eye view of the completed gym floor. The Rib Lake vinyl on the east wall has also been installed
What's Happening?
Significant progress has been made over the past two weeks on the Rib Lake Addition despite the frigid temperatures! Exterior branding is now prominently in place, with large “RL” logos installed on both the north and south elevations. Inside the building, vinyl wall graphics have been completed, providing the final visual touches to the corridor areas.
The final major milestone—the installation of the new bleachers—is scheduled for next week. Following this installation, the team will transition into deep cleaning and final touches in preparation for owner turnover.
Looking ahead, planning and coordination for upcoming project phases are well underway. Work will soon begin in the existing High School Gym, which will be transformed into the new Band and PAC spaces. This summer, construction efforts will then shift to the Kitchen area for a full renovation of that space!
|

The exterior signage on the gymnasium has been installed.
|

The Rib Lake vinyl graphic has been installed in the long corridor.
|
Past Work
- Middle School Corridor Flooring
- North Vestibule Metal Panel
- Vinyl Wall Graphics
- Final Cleaning
Upcoming Work
DID YOU KNOW?
The vinyl graphics have been installed this week at Rib Lake School District. To install these graphics, the entire image is broken up into various sized strips that are then installed next to each other making the final product appear to be one large graphic. To help with this process, heat is applied to the vinyl which allows it to stretch over bumps and in grooves, ensuring the vinyl will adhere to the wall without rips or air bubbles.
Questions?
Project Manager, Ryan Treichel / 414.323.0611 / rtreichel@findorff.com
Superintendent, Jeremy Rosenthal / 608.287.8083 / jrosenthal@findorff.com