RIB LAKE SCHOOL DISTRICT
EXECUTIVE SUMMARY
PROVIDED BY FINDORFF
1200 North Street, Rib Lake, WI 12.23.2025

The wood flooring has been installed and sanded. The next step is to put the finish coats on and prepare for painting.
What's Happening?
A lot of exciting updates over the last two weeks! Work is continuing in the addition as the gym is starting come together nicely following the install of the gym equipment. The gym floor installers arrived this week and they made quick work of the floor. Over the next two weeks the finishing crew will begin painting lines and putting the finish on the floor.
Other parts of the addition are nearing completion as casework and flooring continues to be installed! The finishing touches are being figured out with the graphics which will be installed in all parts of the addition and nearby areas.
As you drive past the front of the addition you will see the metal panels wrapping up in a few short weeks with the new exterior signage being installed next week as well.
The finish line is in sight, and we cannot wait to showcase the new addition to the community!
|

The new flooring in the corridor has been wrapped up.
|

The metal trims have been installed on the North side of the building as we prepare for metal panel to begin on that side
|
Past Work
- Bathroom Partition Installation
- Painting throughout Addition Spaces
- Gymnasium Equipment Installation
- Addition corridor flooring
Upcoming Work
- Gymnasium Wood Floor Finishing
- Concessions Stand Coiling Door
- Concessions Stand Casework
- Bathroom Accessories
|

Metal panel on the south side of the building is receiving its finishing touches.
|

The plywood has been laid out in the gym and the wood flooring has been dispersed ready for installation.
|
DID YOU KNOW?
The holiday season always brings time with family, good food, and lots of travel. This year it is forecasted that 122.4 million Americans will travel at least 50 miles away from home over the holiday season. Car travel is the most popular, accounting for approximately 109.5 million of those travelers.
The metal trims have been installed on the North side of the building
as we prepare for metal panel to begin on that side.
Questions?
Project Manager, Ryan Treichel / 414.323.0611 / rtreichel@findorff.com
Superintendent, Jeremy Rosenthal / 608.287.8083 / jrosenthal@findorff.com